For this new-build project in Bolton, our team were enlisted to carry out piling in line with structural engineers’ calculations from JC Structural Solutions and Architects’ plans from Springett Associates. The images perfectly depict the process we undertake!
- Excavate the ground where piling is needed
- Install the steel piles to ‘set’ (when the piles cannot go any further into the ground)
- Cover these with the reinforced steel beams
- Complete the job with concrete in these areas
For this job, we are on-site for just under 5 days. Take a look at some images from the week below.